theknowledgecapsule.com

CASE SUMMARY ON M/S LANCOR HOLDINGS LTD. V.PREM KUMAR MEMON & ANR. (2025 SC 444)“Mere Delay in Pronouncement of Award is Not Sufficientfor Setting it Aside; Material Prejudice or Patent IllegalityMust Be Established”FACTS OF THE CASE:-

  1. The respondents, who are real brothers, are the owners of a
    land measuring approximately 1.116 acres located at St.
    Mary’s Road, Chennai. They intended to commercially
    develop the property and therefore entered into a Joint
    Development Agreement (JDA) dated 17.12.2004 with
    Lancor Gesco Properties Ltd. (later amalgamated into
    Lancor Holdings Ltd.), the appellant–developer.
  2. Under the terms of the JDA, the developer undertook to
    construct a multi-storeyed commercial building at its own
    cost. In exchange, both parties were to share the developed
    property in the ratio of 50% constructed area each, along
    with a corresponding 50% undivided share in the land.
  3. The developer paid refundable, interest-free security
    deposits totaling ₹6.82 crore to the landowners, which
    were required to be returned to the developer 15 days after
    the “Handover Date”, i.e., the date on which construction
    was completed and the building was certified fit for
    occupation as per the agreement.
  4. A Supplemental Agreement dated 29.03.2006 confirmed
    the appointment of M/s Natraj & Venkat as the Project
    Architect and finalized the floor-wise allocation of the
    constructed area between the landowners and the
    developer. The building was named “Menon Eternity”.
  5. The developer claimed that the construction was
    completed by 2008 and relied on certificates of
    completion/occupation issued by the CMDA, Chennai
    Corporation, and other authorities to assert that the
    building was fit for use. Accordingly, it sought return of
    the security deposits and offered to hand over the
    landowners’ share.
  6. The respondents, however, disputed the completion,
    alleging that several major structural and finishing works
    remained incomplete, including issues with staircases,
    basements, and canopy structures, and therefore contended
    that the “Handover Date” had not arisen.
  7. During this period of dispute, the developer executed five
    registered sale deeds on 19.12.2008 in its own favour,
    transferring to itself portions of the property falling in its
    share, by using a photocopy of an irrevocable Power of
    Attorney that was meant to be released only upon the
    Handover Date and whose original was still deposited with
    an escrow agent, HDFC.
  8. That alleging unauthorized execution of sale deeds and
    breach of contractual obligations, the respondents initiated
    litigation and arbitration proceedings. The developer also
    invoked the arbitration clause and a sole arbitrator (Retd.
    Justice K.P. Sivasubramaniam) was eventually appointed.
  9. The arbitration hearings concluded on 28.07.2012, but the
    award was delivered nearly 3 years and 8 months later on
    16.03.2016 without any explanation for the delay. The
    arbitrator held the sale deeds illegal, yet failed to resolve
    the core dispute regarding compensation, restitution, or the
    final settlement of rights, effectively leaving parties to
    pursue fresh litigation or fresh arbitration.
    ISSUES RAISED IN THE CASE:-
  10. Whether the construction of the building was completed as
    per the terms of the Joint Development Agreement?
  11. Whether the conditions for the “Handover Date” were
    fulfilled so as to require the landowners to refund the
    security deposits?
  12. Whether the Architect’s Completion Certificate dated
    10.10.2008 is valid and binding?
  13. Whether the developer was justified in executing the five
    sale deeds in its own favour using the escrowed Power of
    Attorney?
  14. Whether the said sale deeds are legal and enforceable or
    liable to be cancelled?
  15. Whether either party is entitled to monetary claims or
    compensation as raised in their respective claims and
    counter-claims?
  16. Whether the arbitral award is vitiated due to the
    unexplained delay in its pronouncement and failure to
    finally resolve the disputes?
    CONTENTIONS RAISED BY THE APPELLANTS:-
  17. The appellant contends that the construction of the
    building was duly completed in 2008 in accordance with
    the JDA and Supplemental Agreements, and that all
    necessary statutory clearances and completion certificates
    were obtained from competent authorities.
  18. It is submitted that once the building was certified fit for
    occupation, the Handover Date stood completed, thereby
    requiring the respondents to refund the security deposits
    within the stipulated time.
  19. The respondents withheld the balance security deposits
    without justification, despite having already returned a part
    of the deposit earlier, which indicates acknowledgment of
    completion.
  20. The appellant argues that the sale deeds executed were
    within its contractual rights, since the developer was
    entitled to its 50% share of constructed area and land under
    the JDA.
  21. The arbitrator erroneously rejected the Completion
    Certificate and failed to appreciate evidence of completion,
    leading to perverse and unreasoned conclusions.
  22. The arbitrator declared the sale deeds invalid but did not
    determine the consequential reliefs, leaving core disputes
    unresolved.
  23. The award was delivered 3 years and 8 months after
    conclusion of hearings, without explanation, causing
    serious prejudice and affecting the fairness of adjudication.
    CONTENTIONS RAISED BY THE RESPONDENTS:-
  24. The respondents contend that various major works,
    structural corrections, and finishing obligations were left
    incomplete, and therefore, the building was not fit for
    occupation as required under Clause 6.
  25. Since the mandatory conditions for completion were not
    fulfilled, the Handover Date never commenced, and
    consequently, no obligation arose to refund the security
    deposits.
  26. The respondents argue that the Project Architect’s
    Certificate was issued prematurely, without actual
    completion, and is therefore not binding or reliable.
  27. The developer wrongfully used a photocopy of the
    escrowed Power of Attorney, which could not have been
    acted upon prior to completion. The sale deeds are
    therefore illegal, void and unenforceable.
  28. The respondents assert that they suffered monetary loss
    due to delay in completion, including loss of prospective
    rent, delay in commercial use, and reputational harm,
    entitling them to compensation.
  29. The arbitrator correctly held the sale deeds void and
    recognized that the construction was incomplete; hence, no
    interference with the award is warranted.
  30. The respondents submit that delay alone is not a ground to
    set aside an award unless bias or prejudice is shown, which
    is not proved by the appellant.
    REASONING GIVEN BY THE HON’BLE SUPREME
    COURT:-
  31. The arbitrator took almost 4 years to pronounce the award
    after the hearings had concluded. The Supreme Court held
    that such a long delay, without any explanation, creates
    doubt about the fairness and accuracy of the decision. It
    affects how well the arbitrator could recall the evidence
    and arguments, and therefore causes prejudice to the
    parties.
  32. The arbitrator declared the five sale deeds executed by the
    developer as invalid, but did not decide what happens next
    for example, who should compensate whom, what amount
    is payable, and how the parties’ rights should be finally
    adjusted. So, instead of closing the matter, the award left
    both parties in the same conflict, forcing them to go to
    court again.
  33. The Supreme Court said that an award must finally resolve
    the dispute, not create new confusion.
  34. The arbitrator himself admitted that the situation was
    “complex” and then simply refused to give a clear
    conclusion. The Supreme Court held that an arbitrator
    cannot avoid deciding the main controversy. This failure
    made the award incomplete and legally unsound.
  35. The Court held that because the award did not determine
    the parties’ rights and liabilities, did not settle the dispute
    completely, and came after an unjustified delay, it was
    perverse, unworkable, and contrary to public policy. Under
    Section 34 of the Arbitration and Conciliation Act, such an
    award must be set aside.
  36. The Hon’ble Supreme Court set aside the arbitral award.
    To avoid restarting everything from the beginning, the
    Court appointed a new arbitrator and directed that the case
    should continue using the evidence already recorded, so
    that no further delay is caused.

Leave a Comment

Your email address will not be published. Required fields are marked *

2
    2
    Your Cart
    The People’s Law Dictionary
    The People’s Law Dictionary
    Qty: 2
    Price: Original price was: $1,000.00.Current price is: $500.00.
    Save $1,000.00
    $1,000.00
    Scroll to Top